Rowledge.org; stuff about Rowledges > Home > tim's Home page > Building a Timber Frame Home > The progress slideshow > 
This is a simple slideshow to illustrate the progress of the build project; we started digging on March 26th 2010.

The start of digging.
26th March

The hole gets bigger.
27th March

Timbers being cut.
30th March

Setting out the footings.
5th April

Footing forms for the front wall.
6th April

Footing forms.
7th April

Footings for the main house to mudroom transition.
9th April

Filling the footings.
12th April

After all that work, strip the forms.
13th April

First few layers of ICF block.
14th April

More blocks.
15th April

Enough block layers to need the scaffolding.
16th April

Last few blocks go up.
19th April

Pouring the walls; 75 tons of concrete go in.
22nd April

Bill helps with mudsills.
29th April

Foundation sealant mambrane.
14th May

More membrane.
16th May

Living room post footings poured.
19th May

Backfilling the garage and some of the foundation wall.
20th May

Building the mudroom/lower floor studwall.
24th May

First timbers arrive for the lower floor.
28th May

Lower floor timbers and the first couple of floor trusses.
3rd June

Floor trusses going up.
5th June

Subfloor and main heating duct installed.
7th June

Subfloor nears completion.
8th June

Main timbers arrive.
14th June

Central core timbers installed same day.
14th June

Core timbers.
14th June

Kitchen & bedroom front wall timbers.
15th June

Lots more timbers.
16th June

With thestructural timbers up, the walls start to go in.
18th June

Garage walls.
22nd June

Back walls.
23rd June

Kitchen end wall.
24th June

Bedroom end wall.
25th June

Last few bits of walls.
27th June

With the porch post footings finally poured, the posts can go in.
29th June

Topping out with the whetting bush!
30th June

I built a wall!
7 July

Bedroom ceiling decking goes up on one side.
13th July

Garage floor poured.
15th July

Bedroom ceiling done.
15th July

Porch and closet area decking.
21st July

Porch decking done.
22nd July

Living room decking.
27th July

Entrance porch decking.
28th July

Main house decking all done.
29th July

Matt, Red and Ryan; all done with the frame, walls and roof structure
17th Aug

The final bit of timber is the iteranl beam across the entrance foyer and pantry wall.
17 Aug

Wrapped up like a present; walls wrapped, roof 'foiled'.
20th Aug

Inside; the view towards the bedroom across the living room.
20th Aug

Inside; back porch view.
20th Aug

Siding support straps, bugscreen, flashing added.
24th Aug

Roof panels arrived in huge crates.
31st Aug

First panels of siding go onto the garage.
2nd Sept

Siding around the back.
3rd Sept

Window trim for the master bedroom.
4th Sept

Upper front siding.
8th Sept

Upper front siding.
8th Sept

11th Sept

Basement subflooring, layer 1.
14th Sept

Trenching for the power & water access.
15th Sept

Porch siding.
17th Sept

Some internal walls for the master bedroom.
19th Sept

Living room bump-out siding.
22nd Sept

Kitchen gable end siding.
28th Sept

Almost complete siding, mostly complete roof panelling.
28th Sept

A garage door, wiring.
4th Oct

Basement floor done, internal walls under way.
4th Oct

Basement walls completed.
5th Oct

The view from the top of the bathroom wall.
7th Oct

7th Oct

19th Oct
Entry hall wall built

19th Oct
Master bathroom tub support frame

23rd Oct
Heatpump installed and hooked up

4th Nov
Fireplace fitted to kitchen/living room wall, plumbed in. Drywall all stacked up and ready to go.

5th Nov
Drywall installed all round kitchen and pantry

7th Nov
Damaged post replaced.

11th Nov
Front door installed. House is now locked up! With internal power hooked up as well we cna heat the place, just in time for cooler weather.

13th Nov
All upstairs drywall done, some downstairs as well. Outside, the last few bits of siding have been completed and the front door trimmed

14th Nov
Front door with all the siding painted.

20th Nov
Drywall taped

20th Nov
and in the bedroom

27th Nov
sub-floor for tiles in the kitchen

28th Nov
Drywall taped, mudded and sanded

1st Dec
The well is connected!

1st Dec
The fire works!